Race direction and timing

My voluntary work as race director and timing operator at FPV drone races, and the planning of a modular "Eurobox" hardware system for the TSV Korntal drone department.

Background​

At an FPV drone race, the race director runs the whole event: venue setup, timing system, heat schedule, frequencies, track walk, pilot briefing and results. Behind every race day is a mobile technical setup of video receivers, timing hardware, a computer, network and screens that has to be set up and taken down each time.

My role and scope​

Since 2025 I have taken on this role on a voluntary basis, separate from my position as deputy head of the TSV Korntal drone department.

EventNumberMy role
Whoop races, TSV Korntal3Organisation and race direction, 20 to 30 pilots each
MultiGP Global Qualifiers, TSV Korntal2Organisation and race direction
FAI and DCS races, Aircrasher chapterregularlyRace direction or timing, considerably larger fields

A sports hall set up for a race

Setting up a sports hall for a race: race control desk, timing, pilot tables and projector screen

Race organisation​

Preparation and setup​

For the races at TSV Korntal I handled the organisation from start to finish:

  • Setting the date and planning all tasks that had to be done before the race.
  • Organising the equipment, such as tables, chairs and the projector.
  • Setting up the venue the evening before: deciding where every station stands and how everything is connected.
  • Setting up the timing computer and configuring all heats.

Race day​

On race day I led the track walk and the pilot briefing and ran the race schedule. Disputes were settled together as a group decision.

At the race control desk during a race

At the race control desk during a race

Timing systems​

Lap times are measured from the 5.8 GHz video signal of each drone, so the drones need no extra transponder. At our races we used ImmersionRC LapRF hardware with LiveTime. Besides that, we tested several other software and hardware options:

SystemType and use
LiveTimeRace software used at our races; assigns frequencies automatically
RotorHazard, FPVTracksideRace software, tested
NuclearHazardTiming hardware for RotorHazard, tested
ImmersionRC LapRFCommercial timing hardware used at our races, borrowed from another club
ZippyDecoderOpen-source decoder (Raspberry Pi with receiver nodes) for LiveTime, tested

Eurobox system​

Status

Planning largely complete (October 2026). Purchasing and the build of the first boxes are still to come.

Problem and objective​

The club's race hardware is spread over many different cases, and cables are often missing at the venue. I am leading the club's switch to a uniform set of Auer Euroboxes. Every box is a pre-wired, plug-in module that can be set up in under two minutes. The system must replace all functions of the old cases and add new ones: live video, video wall, network and streaming, timing and RF monitoring.

System architecture​

BoxContentsConnectionStatus
EventVRX box AHDZero EventVRX 4-channel receiver and captureUSB 3 to laptopactive
EventVRX box BHDZero EventVRX 4-channel receiver and captureUSB 3 to laptopactive
Video wall box2×2 controller for 4 monitorsHDMI from laptopactive
Network boxLTE router and PoE+ switchLAN to laptop, timer and SDRactive
Laptop / OBS boxRace control and streaming–on hold
Timer boxNuclearHazard timer, powered over PoEPoE+on hold
HackRF boxWeb SDR for 5.8 GHz band monitoringLANon hold

Mains power (230 V) is daisy-chained from box to box (C14 in, C13 out, max. 10 A). Each box contains a Mean Well 12 V power supply with a fused output for every device. The two EventVRX boxes have forced ventilation with dust filters, and the receivers' antenna connectors go straight through the box wall.

Standards, safety and budget​

  • Common standards: connectors only on the sides, real panel-mount sockets instead of loose couplers, 3D-printed handles, mounts and connector plates.
  • Cables: every box carries its own cables; a five-colour code with matching rings at both cable ends shows which cable belongs to which box.
  • Electrical safety: 230 V internal wiring with protective earth, fused 12 V distribution, printed touch guards, inspection by a qualified electrician planned.
  • Budget: target approx. EUR 800. The active scope (two EventVRX boxes, video wall, network, cables, labelling) comes to approx. EUR 695–715. Re-sourcing the panel-mount connectors cut their cost from approx. EUR 96 to EUR 72. Laptop, HackRF and timer boxes (approx. EUR 450–530) were deliberately put on hold to stay within budget.

The planning is documented with layout plans, parts and cable lists, signal and power diagrams and cost breakdowns.

Result​

Feedback from pilots on the races has always been very positive. At our last MultiGP Global Qualifier, held early in the season, the four fastest times worldwide were briefly set at our event, and one time from our qualifier finished in the global top 10.

Key figureValue
Races directed at TSV Korntal5 (3 Whoop races, 2 MultiGP Global Qualifiers)
Pilots per Whoop race20–30
Timing at racesImmersionRC LapRF with LiveTime
Eurobox budget (active scope)approx. EUR 700 of EUR 800

Conclusion​

Running races combines organisation, technology and communication: the event only works if the schedule, the timing system and the people on site work together. Testing several timing systems showed how much a reliable hardware base that is quick to set up matters on race day.

Outlook. The Eurobox system turns this experience into a standard setup. Once the first boxes are built, setup time at every race will drop and missing cables will no longer be an issue.