Race gates for the MultiGP European Championship 2026

Design, documentation and build of the race gates for the 2nd MultiGP European Championship (11–13 September 2026, Aichtal, Germany).

Single and double gates on the championship track

Single and double gates on the championship track (Photo: MultiGP)

Background​

The 2nd MultiGP European Championship took place from 11 to 13 September 2026 at the SV07 Aich sports ground in Aichtal near Stuttgart. It was hosted by the chapters Aircrasher and Bavarian Multirotor, Europe's two largest MultiGP chapters. 104 pilots from around 21 countries took part. The total event budget was about EUR 23,000.

Race gates of this size at international events often bend heavily in wind and have to be held up with guy lines. For this championship a new set of gates was needed that is stable, can be assembled by volunteers and carries printed sponsor banners.

Objective​

Design and build a complete set of obstacles (4 double gates, 5 single gates and 10 flags) from aluminium tubing and standard tube connectors. The gates must stand without guy lines, be quick to assemble and dismantle, and fit printed fabric covers with sponsor logos.

My role​

I was a co-organiser of the event and part of the 7-person organising team. For the gates, my responsibilities were the design, the technical documentation, the specification of the fabric covers and the track build on site. I also set up regular team meetings so that everyone was aligned on tasks, timeline and status.

Gate system and components​

The gates are built as a modular tube-clamp system. The whole set uses only seven standard tube lengths, which keeps ordering, transport and assembly simple.

ComponentUse
Aluminium tubes, 7 lengths (0.5 m to 4.8 m)Posts, crossbars, foot tubes and braces
Galvanised steel tube connectors (T-pieces, 90° elbows)Fixed joints between posts, crossbars and foot tubes
Fixed 45° connectors (galvanised steel)Diagonal braces between post and foot tube, corner braces on the double gate
Printed fabric covers with hem tunnelsSponsor branding, slid over the tubes
ObstacleQuantityMain dimensions
Single gate52.9 m wide, 2.4 m posts, 2.9 m foot tubes
Double gate4Two gates stacked, 4.8 m posts, corner braces in the lower gate
Flag103.8 m pole on a braced T-base

The key to stability is the foot: each post stands on a long foot tube and is supported by a 1 m diagonal brace. The brace is attached to the post and the foot tube with fixed 45° connectors, so the same parts fit every gate.

CAD model​

I modelled the gates in FreeCAD with the same connectors as the real build, including the fixed 45° connectors for the braces and the 90° elbows at the top corners, to check dimensions and part lists before ordering.

Single gate in FreeCAD

Single gate

Double gate with corner braces in FreeCAD

Double gate with corner braces

Foot brace with fixed 45° connectors

Foot brace with fixed 45° connectors

Corner brace of the double gate

Corner brace of the double gate

Build guides and cutting guide​

So that helpers could assemble the gates without me, I created two A4 build guides in draw.io. Every tube length has its own colour, and every joint shows a photo of the connector to use.

Build guide, front: single gate and flag

Build guide, front: single gate and flag

Build guide, back: double gate

Build guide, back: double gate

The fabric covers are slid over the tubes through sewn hem tunnels. Where a tube connector sits, the tunnel has to be opened. The cutting guide shows for each banner exactly where to cut it fully, where to open only the back of the hem, and which parts of the double gate are opened at the back.

Cutting guide for the printed fabric covers

Cutting guide for the printed fabric covers (dimensions in cm)

Fabric covers and supplier issue​

I calculated the dimensions of all fabric covers, including the hem tunnels, from the tube diameters and the gate geometry. The covers were then ordered from a textile printer.

Supplier error

The first delivery came out about 6 cm too small everywhere. The manufacturer's online instructions defined the hem tunnel as a diameter, but production treated the value as a flat measurement. I traced the error back to their documentation and proved that my calculation was correct. The supplier remade the covers, and the corrected fabric arrived only one week before the event.

Assembly and track build​

The team assembled the gates using the build guides. I drew sketches for the larger scaffolding structures, which were built by a scaffolding contractor, and briefed the contractor on site. During the event setup I built the track and helped wherever needed.

Single gate with fabric cover

Single gate with fabric cover

Foot with diagonal brace and 45° connectors

Foot with diagonal brace and 45° connectors

All gates assembled and ready for the track

All gates assembled and ready for the track

Result​

All 19 obstacles were delivered and installed on schedule and held up through the full three-day championship, including night racing with LED-lit gates. Even in fairly strong wind the gates stayed upright without any guy lines, secured only with simple ground anchors made from bent rebar. Pilots and organisers gave positive feedback in person.

The complete gate set was built by two people in two full working days. The year before, a team of about seven people worked on and off for four days, including nights, to build wooden gates that were thrown away after the event.

Key figureValue
Pilots / countries104 / approx. 21
Obstacles4 double gates, 5 single gates, 10 flags
Standard tube lengths7
Build effort2 people, 2 days (previous year: approx. 7 people, 4 days and nights, single-use wooden gates)
Guy linesNone needed
Ground anchors (bent rebar)4 per double gate, 2 per single gate, 1 per flag
Material costGates approx. EUR 5,000, fabric approx. EUR 2,500

The championship track by day

The championship track by day (Photo: MultiGP)

The track at dusk

The track at dusk (Photo: RadioMaster)

Conclusion​

The modular gate system met all goals: it is stable without guy lines and needs only a few simple rebar anchors, can be assembled by helpers with the build guides, and gives sponsors a clean, professional surface. The project combined mechanical design, technical documentation, supplier management and teamwork under a fixed deadline.

Lessons learned. Investing time in planning and CAD up front pays off: standard parts and good documentation cut the build effort from about seven people over four days to two people in two days. Supplier specifications should be checked against a sample before the full order, especially for custom dimensions.

Outlook. Unlike the single-use wooden gates of the previous year, the gates are reusable and can be adapted for further events with the same parts and documentation.